Page Versions (plan revisions) & As-Bid Snapshots Coming ​

ComingThis feature is designed but not in DimSum yet. This page describes how it will work.

Load Revision 2 of a sheet as a new version of the same page, line it up with the 4-click Overlay & Align, view the old, the new or both overlaid, keep every old version forever — and freeze the whole takeoff as an As-Bid Snapshot you can compare against later.

Overview ​

Plans change mid-bid. The architect sends Revision 2 of A-101, and the estimator has to find what changed and fix the takeoff without losing the work already done.

the answer: "Add new page version, where we can turn on one, both, or fully replace it. But the old version should never go away." So a page in DimSum can hold several versions of its sheet:

  • Your takeoffs stay on the page, not on a particular version, so nothing has to be redrawn.
  • Each new version inherits the page's scale and alignment, but can be given its own scale, its own alignment, or even a different sheet/location when the revision moved things.
  • You choose what to see: the current version, a previous version, or both overlaid in contrasting tints (like Overlay & Align), so changes jump out.
  • Old versions are never deleted, and everything travels with the file — including Export for Sharing.
  • An As-Bid Snapshot freezes the whole takeoff at bid time ("Bid 1 – 9/22") so you can see exactly what changed after a revision.

Where to find it ​

  • Right-click a page in the Project Tree → Add new page version…
  • Page ribbon tab → Page Versions dropdown: Add new version, View current / previous / both, Make current.
  • Page Properties → Version field.
  • The tree shows a version badge on the page: A-101 · v2.
  • As-Bid Snapshots: Project menu → Snapshots (take a snapshot, list them, compare).
  • A page with a newer version loaded also shows up as a row in the Refresh Center, where you can switch or compare.

How to use it ​

Add a new version (Revision 2 arrives) ​

  1. Right-click the page (e.g. Page 3 – A-101 Main Floor Plan) → Add new page version…
  2. Pick the file (e.g. A-101 Rev2.pdf) and, for multi-page files, the page within it. It imports and converts like any plan (Plan import).
  3. Optionally type a revision label (e.g. "Rev 2 – 10/14 addendum").
  4. Align it with the 4 clicks: a corner on the old version, the same corner on the new one, a second corner on the old, the same on the new. Backspace picks up a wrong click. See Overlay & Align.
  5. The new version inherits the page's scale and alignment and becomes the current version. The tree badge changes to · v2.
  6. If the revision changed things, override what you need on the version itself — it can have its own scale, its own alignment, or be a different sheet at a different location (the architect moved the plan on the sheet, or re-issued it on a different sheet number). DimSum prompts to verify the scale when it looks different.

Check your takeoff against the new version ​

  1. Page Versions → View both. The old version shows in one tint, the new one in another, with an opacity slider.
  2. Pan around: anything drawn in only one tint has changed (a moved wall, a new window, a deleted room).
  3. Adjust your takeoffs on the page: drag vertices, add or remove shapes. Your tools sit on top of whichever version(s) you're viewing.
  4. Mark changed areas with a Revision Cloud if you want a record (Annotation tools).
  5. Page Versions → View current when you're done.

Look at an older version ​

  1. Page Versions → View previous (or pick a specific version from the list).
  2. The canvas shows that version's plan with your current takeoffs on top.
  3. Switch back with View current.

Switch fully to a version ("fully replace") ​

  1. Page Versions → pick a version → Make current.
  2. From now on the page shows that version by default, prints it and reports it. The other versions are kept.

Compare side by side instead ​

Open the page in two panes, set each pane to a different version, and turn on Sync Views (Split views). The version shown is a per-pane setting.


As-Bid Snapshots ​

A page version tells you what the plan said. A snapshot tells you what your takeoff said.

Take a snapshot ​

  1. Finish the takeoff you're about to send out.
  2. Project → Snapshots → Take snapshot.
  3. Name it — the default is the bid name and date, e.g. "Bid 1 – 9/22".

The snapshot freezes the whole takeoff: every instance and its quantities, the prices in force at that moment, and the report output. It sits inside the .dsum and is never touched by later edits.

Compare after a revision ​

  1. Load the new page version(s) and fix the takeoff as usual.
  2. Project → Snapshots → pick "Bid 1 – 9/22" → Compare with now.
  3. You get a change list: instances added, removed and changed, with old → new quantities and prices, and a total difference. Each row has "Show on plan".

💡 Take a snapshot every time you send a number out. It costs nothing and it's the only way to answer "what changed since the bid?" later.

Rules ​

  • A snapshot is read-only; it can be renamed and deleted, but never edited.
  • Snapshots travel with the .dsum, including Export for Sharing.
  • Comparison is between a snapshot and the live takeoff, or between two snapshots.

Options & settings ​

SettingWhat it doesDefault
Current versionThe version shown, printed and reported by defaultNewest added
View modeCurrent / Previous / Specific version / Both overlaidCurrent (per pane)
Overlay tints and opacityColors and transparency when viewing bothSame as Overlay & Align (old = gray/black, new = red/blue)
Revision labelFree-text label per version, e.g. "Rev 2"Empty
Version alignmentThe 4-click alignment of this versionInherited from the page; overridable per version
Version scaleThis version's scaleInherited from the page; overridable per version
Version sourceThe file/sheet and location this version came fromCan differ from the previous version
SnapshotsNamed frozen copies of the takeoff (As-Bid)None
{Page > Version}Version number/label for formulas, stamps and reportsCurrent version

Examples ​

  • Addendum mid-bid: A-101 Rev 2 moves the garage wall back 2'. Add new page version, align on two house corners, View both: the garage wall shows twice in two tints. Drag the wall takeoff vertices to the new line; the wall LF updates. Reports print "A-101 · v2".
  • Customer asks "what did you bid?": View previous on A-101: the plan you bid on is still there, with the same takeoff on top.
  • Wrong revision loaded: Make current on v1; the Rev 2 you loaded by mistake stays in the list (it's never deleted) but is no longer shown.
  • Revision on a different sheet: Rev 3 of the main floor plan is issued as A-101.1 at 3/16" instead of 1/4". Add it as a version of the same page, give the version its own scale and alignment, and the takeoff carries over.
  • "What changed since the bid?": snapshot "Bid 1 – 9/22" before sending; three weeks and two addenda later, Compare with now shows +42 LF of exterior wall, 6 more posts and a $1,180 difference.

Tips & shortcuts ​

  • Align versions on the same two corners you used for level alignment; they're usually the best-drawn points on the sheet.
  • Use "View both" with a low opacity on the old version so the new plan reads clearly.
  • Add a revision label as you load it; "v3" means little six weeks later, "Rev 3 – window changes" means a lot.

Rules, limits & edge cases ​

  • Versions cannot be deleted (by design), and none are dropped from exports.
  • Takeoffs are not copied per version; there is one set of tools per page. To keep the takeoff as it was when you bid it, take an As-Bid Snapshot (above) rather than duplicating the page.
  • A version drawn at a very different layout (sheet re-drawn from scratch, building moved on the sheet) still aligns with the 4 clicks; a version that is mirrored cannot.
  • Automatic change highlighting (DimSum marking what changed) is v1.1; in v1 you spot changes by viewing both versions overlaid.
  • Protected pages: all versions of a protected page are protected, and the whole page stays hidden everywhere until the project password is entered (protected pages).
Planbase Estimating LLCDimSum Takeoff
Sheet titlePage Versions (plan revisions) & As-Bid Snapshots
SectionPlans & pages
StatusComing
ScaleNTS
Sheet12 / 57